29INR0188 · Solar · Pecos County
Star Of Texas Solar
Star Of Texas Solar is a 415 MW solar project in Pecos County, Texas, connecting at 60152 Fort Stockton Switch 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0188
- Capacity
- 415 MW
- Fuel
- Solar (PV)
- Substation
- 60152 Fort Stockton Switch 345kV
- County
- Pecos County
- Interconnecting entity
- BOULEVARD ASSOCIATES, LLC
- Projected COD
- 07/01/2029
- Entered queue
- 08/12/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/12/2025Entered the queue with 415 MW, projected COD 07/01/2029
- 08/12/2025Screening → FIS Requested