29INR0169 · BESS · Zapata County

Falcon BESS

Falcon BESS is a 517 MW battery storage project in Zapata County, Texas, connecting at Tap 345kV #80225 CENIZO to #80307 DEL SOL. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0169
Capacity
517 MW
Fuel
BESS (BA)
Interconnecting entity
Falcon Energy Project, LLC
Projected COD
12/01/2029
Entered queue
08/28/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/28/2025
    Entered the queue with 517 MW, projected COD 12/01/2029
  • 08/28/2025
    Screening → FIS Requested