LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0146 · Wind · Duval County

Estrella Dorada Wind

Estrella Dorada Wind is a 306 MW wind project in Duval County, Texas, connecting at Tap 345 kV 80079 Cruce - 5901 San Miguel Ckt 2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/13/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0146
Capacity
306 MW
Fuel
Wind (WT)
Interconnecting entity
Estrella Dorada Wind Farm, LLC
Projected COD
07/13/2029
Entered queue
07/17/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/17/2025
    Entered the queue with 306 MW, projected COD 07/13/2029
  • 07/17/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.