29INR0132 · BESS · Borden County

Caesar Storage

Caesar Storage is a 206 MW battery storage project in Borden County, Texas, connecting at 59916 Buck Canyon 345 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/26/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0132
Capacity
206 MW
Fuel
BESS (BA)
Interconnecting entity
Caesar Solar, LLC
Projected COD
11/26/2029
Entered queue
07/07/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/15/2026
    FIS Requested → IA Signed
  • 07/07/2025
    Entered the queue with 206 MW, projected COD 11/26/2029
  • 07/07/2025
    Screening → FIS Requested

Other projects at this substation

Caesar SolarSolar182 MWIA Signed