29INR0125 · BESS · Duval County
Apricot Sun Storage
Apricot Sun Storage is a 201 MW battery storage project in Duval County, Texas, connecting at Tap 80079 (Cruce) - 5901 (San Miguel) 345 kV Ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0125
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Duval County
- Interconnecting entity
- Apricot Sun Energy Center, LLC
- Projected COD
- 09/30/2029
- Entered queue
- 03/30/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/30/2025Entered the queue with 201 MW, projected COD 09/30/2029
- 03/30/2025Screening → FIS Requested
Other projects at this substation
| Apricot Sun Solar | Solar | 201 MW | FIS Requested |