29INR0058 · Solar · Milam County
Brahman Renewables Solar
Brahman Renewables Solar is a 101 MW solar project in Milam County, Texas, connecting at Tap Voss Lake switch #3751 – Badger Switch #3761 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0058
- Capacity
- 101 MW
- Fuel
- Solar (PV)
- County
- Milam County
- Interconnecting entity
- Brahman Renewables
- Projected COD
- 05/01/2029
- Entered queue
- 10/29/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/09/2025Screening → FIS Requested
- 10/29/2024Entered the queue with 101 MW, projected COD 05/01/2029
Other projects at this substation
| Brahman Renewables Storage | BESS | 207 MW | FIS Requested |