29INR0041 · Gas · Austin County
Homestead Power (TEF-Due Diligence)
Homestead Power (TEF-Due Diligence) is a 260 MW natural gas project in Austin County, Texas, connecting at 138 kV New Bremen #7271. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/15/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0041
- Capacity
- 260 MW
- Fuel
- Gas (GT)
- Substation
- 138 kV New Bremen #7271
- County
- Austin County
- Interconnecting entity
- Homestead Power LLC
- Projected COD
- 12/15/2029
- Entered queue
- 07/29/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/29/2024Entered the queue with 260 MW, projected COD 12/15/2029
- 07/29/2024Screening → FIS Requested
Other projects at this substation