29INR0040 · Wind · Glasscock County
Gusty Windpower
Gusty Windpower is a 249 MW wind project in Glasscock County, Texas, connecting at Tap 345kV 59903 Bearkat - 1058 Longshore_5; Anemone 345 kV Station. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0040
- Capacity
- 249 MW
- Fuel
- Wind (WT)
- County
- Glasscock County
- Interconnecting entity
- Gusty Windpower, LLC
- Projected COD
- 12/31/2028
- Entered queue
- 07/30/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/03/2025FIS Requested → IA Signed
- 08/20/2024Screening → FIS Requested
- 07/30/2024Entered the queue with 249 MW, projected COD 12/31/2028
Other projects at this substation