29INR0030 · Solar · Briscoe County
Commodus Solar
Commodus Solar is a 502 MW solar project in Briscoe County, Texas, connecting at Tap 345kV 23914 Tule Canyon - 23900 Alibates. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/30/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0030
- Capacity
- 502 MW
- Fuel
- Solar (PV)
- County
- Briscoe County
- Interconnecting entity
- IP Blackwell, LLC
- Projected COD
- 07/30/2029
- Entered queue
- 07/11/2024
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/11/2024Entered the queue with 502 MW, projected COD 07/30/2029
- 07/11/2024Screening → FIS Requested
Other projects at this substation
| Commodus Wind | Wind | 641 MW | FIS Requested |