29INR0025 · Wind · Pecos County

Skyrider Wind

Skyrider Wind is a 370 MW wind project in Pecos County, Texas, connecting at 138kV #38365 TNPINION. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0025
Capacity
370 MW
Fuel
Wind (WT)
Interconnecting entity
NextEra Energy Interconnection Holdings, LLC
Projected COD
07/01/2028
Entered queue
10/29/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/23/2025
    FIS Requested → IA Signed
  • 10/29/2024
    Entered the queue with 370 MW, projected COD 07/01/2028
  • 10/29/2024
    Screening → FIS Requested