LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0019 · Solar · Howard County

Infinium Solar

Infinium Solar is a 402 MW solar project in Howard County, Texas, connecting at #1058 Longshore Switch - #18548 Prairieland Switch 345kV Ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0019
Capacity
402 MW
Fuel
Solar (PV)
Interconnecting entity
Jackalope Flats Solar, LLC
Projected COD
07/01/2029
Entered queue
07/18/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/18/2024
    Entered the queue with 402 MW, projected COD 07/01/2029
  • 07/18/2024
    Screening → FIS Requested

Other projects at this substation