29INR0015 · Solar · Jones County

Funston Solar

Funston Solar is a 351 MW solar project in Jones County, Texas, connecting at tap 345 kV 68000 West Shackelford – 68004 Phantom Hill Circuit 2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/26/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0015
Capacity
351 MW
Fuel
Solar (PV)
Interconnecting entity
Funston Solar LLC
Projected COD
02/26/2027
Entered queue
02/27/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 07/01/2027 → 02/26/2027 (-4 months)
  • 12/17/2025
    FIS Requested → FIS Approved
  • 10/23/2024
    FIS Approved → IA Signed
  • 03/19/2024
    Screening → FIS Requested
  • 02/27/2024
    Entered the queue with 351 MW, projected COD 07/01/2027

Other projects at this substation