28INR0530 · Gas · Brazos County
Wickson Creek Gas
Wickson Creek Gas is a 1,022 MW natural gas project in Brazos County, Texas, connecting at Jack Creek Station 345 kV (#975). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0530
- Capacity
- 1,022 MW
- Fuel
- Gas (GT)
- Substation
- Jack Creek Station 345 kV (#975)
- County
- Brazos County
- Interconnecting entity
- Wickson Creek Center, LLC
- Projected COD
- 10/01/2028
- Entered queue
- 06/04/2026
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/04/2026Entered the queue with 1,022 MW, projected COD 10/01/2028
- 06/04/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.