28INR0476 · Solar · Foard County

Pease River Solar

Pease River Solar is a 276 MW solar project in Foard County, Texas, connecting at Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0476
Capacity
276 MW
Fuel
Solar (PV)
Interconnecting entity
Pease River Solar LLC
Projected COD
06/30/2029
Entered queue
11/17/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/17/2025
    Entered the queue with 276 MW, projected COD 06/30/2029
  • 11/17/2025
    Screening → FIS Requested

Other projects at this substation

Daisy SolarSolar201 MWFIS Requested
Big Field SolarSolar506 MWScreening