28INR0476 · Solar · Foard County
Pease River Solar
Pease River Solar is a 276 MW solar project in Foard County, Texas, connecting at Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0476
- Capacity
- 276 MW
- Fuel
- Solar (PV)
- County
- Foard County
- Interconnecting entity
- Pease River Solar LLC
- Projected COD
- 06/30/2029
- Entered queue
- 11/17/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/17/2025Entered the queue with 276 MW, projected COD 06/30/2029
- 11/17/2025Screening → FIS Requested
Other projects at this substation
| Daisy Solar | Solar | 201 MW | FIS Requested |
| Big Field Solar | Solar | 506 MW | Screening |