28INR0474 · BESS · Bexar County
Mission Station Energy Storage I
Mission Station Energy Storage I is a 375 MW battery storage project in Bexar County, Texas, connecting at Tap 345kV (Bus #5400) SPRUCE – (Bus #5475) VON_ROSE Ckt 1;. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/31/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0474
- Capacity
- 375 MW
- Fuel
- BESS (BA)
- County
- Bexar County
- Interconnecting entity
- Mission Station LLC
- Projected COD
- 05/31/2030
- Entered queue
- 02/04/2026
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/04/2026Entered the queue with 375 MW, projected COD 05/31/2030
- 02/04/2026Screening → FIS Requested
Other projects at this substation