LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0473 · BESS · Hill County

Seven Angels Energy Storage II

Seven Angels Energy Storage II is a 514 MW battery storage project in Hill County, Texas, connecting at 68090 Sam Switch Bus 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0473
Capacity
514 MW
Fuel
BESS (BA)
Interconnecting entity
Seven Angels Infrastructure LLC
Projected COD
12/31/2028
Entered queue
11/04/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/04/2025
    Entered the queue with 514 MW, projected COD 12/31/2028
  • 11/04/2025
    Screening → FIS Requested

Other projects at this substation

Seven Angels Energy Storage IBESS514 MWFIS Requested