28INR0464 · Solar · Wilbarger County
Grayback Solar
Grayback Solar is a 222 MW solar project in Wilbarger County, Texas, connecting at Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B.. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0464
- Capacity
- 222 MW
- Fuel
- Solar (PV)
- County
- Wilbarger County
- Interconnecting entity
- Grayback Solar, LLC
- Projected COD
- 09/01/2029
- Entered queue
- 10/14/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/14/2025Entered the queue with 222 MW, projected COD 09/01/2029
- 10/14/2025Screening → FIS Requested
Other projects at this substation
| Limitless Energy Hub I | Gas | 1,238 MW | IA Signed |
| Limitless Energy Hub II | Gas | 1,238 MW | IA Signed |
| H&C WILBARGER POWER I | Gas | 1,026 MW | FIS Requested |
| H&C WILBARGER POWER II | Gas | 1,026 MW | FIS Requested |