28INR0432 · BESS · Kaufman County

Solarville BESS SLF

Solarville BESS SLF is a 0 MW battery storage project in Kaufman County, Texas, connecting at Tap 345 kV (#2432)Tri Corner - (#3105) Elkton. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/19/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0432
Capacity
0 MW
Fuel
BESS (BA)
Interconnecting entity
Ville Solar, LLC
Projected COD
09/19/2028
Entered queue
11/07/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/07/2025
    Entered the queue with 0 MW, projected COD 09/19/2028
  • 11/07/2025
    Screening → FIS Requested