28INR0413 · Gas · Reeves County

Tolivar Power Plant Phase 2

Tolivar Power Plant Phase 2 is a 224 MW natural gas project in Reeves County, Texas, connecting at Tap 138 KV 38055 Saltdraw-38043 COWPEN. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/29/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0413
Capacity
224 MW
Fuel
Gas (IC)
Interconnecting entity
Pecos Power Plant, LLC
Projected COD
09/29/2027
Entered queue
07/07/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/14/2026
    FIS Approved → IA Signed
  • 02/25/2026
    FIS Requested → FIS Approved
  • 07/07/2025
    Entered the queue with 224 MW, projected COD 09/29/2027
  • 07/07/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.