28INR0408 · Wind · Haskell County
Max 4 Wind
Max 4 Wind is a 353 MW wind project in Haskell County, Texas, connecting at Tap 345 kV Gauss7D (Bus# 60703) to Quasar7A (Bus# 60712) Transmission Line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0408
- Capacity
- 353 MW
- Fuel
- Wind (WT)
- County
- Haskell County
- Interconnecting entity
- Lake Creek Wind, LLC
- Projected COD
- 08/31/2029
- Entered queue
- 07/16/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/16/2025Entered the queue with 353 MW, projected COD 08/31/2029
- 07/16/2025Screening → FIS Requested