28INR0340 · Wind · Zapata County
Corralitos Wind 4
Corralitos Wind 4 is a 195 MW wind project in Zapata County, Texas, connecting at ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C - 80307 DELSOL7C). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0340
- Capacity
- 195 MW
- Fuel
- Wind (WT)
- County
- Zapata County
- Interconnecting entity
- Las Crestas Wind Energy, LLC
- Projected COD
- 05/31/2028
- Entered queue
- 06/13/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/24/2025Screening → FIS Requested
- 06/13/2025Entered the queue with 195 MW, projected COD 05/31/2028
Other projects at this substation
| Corralitos Wind 3 | Wind | 196 MW | FIS Requested |