ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0335 · Solar · Navarro County

Oak Valley Solar

Oak Valley Solar is a 251 MW solar project in Navarro County, Texas, connecting at 68091 (Navarro) (345). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/28/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0335
Capacity
251 MW
Fuel
Solar (PV)
Interconnecting entity
Oak Valley Solar LLC
Projected COD
09/28/2029
Entered queue
03/19/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/19/2025
    Entered the queue with 251 MW, projected COD 09/28/2029
  • 03/19/2025
    Screening → FIS Requested