28INR0325 · Gas · Duval County
Cielo Vista Power Gas Plant
COD delayed 1×
Cielo Vista Power Gas Plant is a 344 MW natural gas project in Duval County, Texas, connecting at Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/30/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0325
- Capacity
- 344 MW
- Fuel
- Gas (IC)
- County
- Duval County
- Interconnecting entity
- Cielo Vista Power, LLC
- Projected COD
- 03/30/2029
- Entered queue
- 08/13/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 06/30/2028 → 03/30/2029 (+9 months)
- 08/13/2025Entered the queue with 344 MW, projected COD 06/30/2028
- 08/13/2025Screening → FIS Requested
Other projects at this substation
| Cielo Vista Solar | Solar | 503 MW | FIS Requested |
| Cielo Vista Storage | BESS | 311 MW | FIS Requested |