28INR0322 · Solar · Ector County
Velociraptor Solar II
Velociraptor Solar II is a 242 MW solar project in Ector County, Texas, connecting at Tap Wolf (#11010) - Reiter Switch (#18544) Ckt1 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0322
- Capacity
- 242 MW
- Fuel
- Solar (PV)
- County
- Ector County
- Interconnecting entity
- Velociraptor Solar II, LLC
- Projected COD
- 12/01/2029
- Entered queue
- 05/12/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/12/2025Entered the queue with 242 MW, projected COD 12/01/2029
- 05/12/2025Screening → FIS Requested
Other projects at this substation
| Velociraptor BESS II | BESS | 246 MW | FIS Requested |