28INR0299 · BESS · Wilson County
Moon Stone BESS
Moon Stone BESS is a 201 MW battery storage project in Wilson County, Texas, connecting at Tap 138kV Eagle Creek (5132) to Floresville (5155). ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 03/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0299
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Wilson County
- Interconnecting entity
- Moon Stone Battery Facility LLC
- Projected COD
- 03/31/2029
- Entered queue
- 02/14/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/14/2025Entered the queue with 201 MW, projected COD 03/31/2029
Other projects at this substation