28INR0299 · BESS · Wilson County

Moon Stone BESS

Moon Stone BESS is a 201 MW battery storage project in Wilson County, Texas, connecting at Tap 138kV Eagle Creek (5132) to Floresville (5155). ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 03/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0299
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Moon Stone Battery Facility LLC
Projected COD
03/31/2029
Entered queue
02/14/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/14/2025
    Entered the queue with 201 MW, projected COD 03/31/2029

Other projects at this substation