28INR0295 · BESS · Brazoria County

Margay Energy Storage

Margay Energy Storage is a 101 MW battery storage project in Brazoria County, Texas, connecting at Tap 138kV 42750 Mykawa - 48353 Telephone Ckt 06. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/10/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0295
Capacity
101 MW
Fuel
BESS (BA)
Interconnecting entity
PowerPulse LLC
Projected COD
04/10/2029
Entered queue
02/24/2025
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/26/2025
    FIS Approved → IA Signed
  • 11/13/2025
    FIS Requested → FIS Approved
  • 02/24/2025
    Entered the queue with 101 MW, projected COD 04/10/2029
  • 02/24/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.