28INR0257 · BESS · Dallas County
watermelon 7 energy storage
watermelon 7 energy storage is a 102 MW battery storage project in Dallas County, Texas, connecting at Tap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1.. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0257
- Capacity
- 102 MW
- Fuel
- BESS (BA)
- County
- Dallas County
- Interconnecting entity
- Tempus power management LLC
- Projected COD
- 03/01/2029
- Entered queue
- 02/06/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/06/2025Entered the queue with 102 MW, projected COD 03/01/2029
- 02/06/2025Screening → FIS Requested
Other projects at this substation
| watermelon 1 energy storage | BESS | 102 MW | FIS Requested |
| watermelon 2 energy storage | BESS | 102 MW | FIS Requested |
| watermelon 4 energy storage | BESS | 102 MW | FIS Requested |
| watermelon 5 energy storage | BESS | 102 MW | FIS Requested |
| watermelon 6 energy storage | BESS | 102 MW | FIS Requested |
| watermelon 8 energy storage | BESS | 102 MW | FIS Requested |