ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0221 · BESS · Wichita County

Rio Star Energy Storage

Rio Star Energy Storage is a 143 MW battery storage project in Wichita County, Texas, connecting at Tap 1464 Wichita Falls South Switch – 1474 Scotland 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/20/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0221
Capacity
143 MW
Fuel
BESS (BA)
Interconnecting entity
Rio Star Energy Storage, LLC
Projected COD
04/20/2029
Entered queue
02/04/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/04/2025
    Entered the queue with 143 MW, projected COD 04/20/2029
  • 02/04/2025
    Screening → FIS Requested

Other projects at this substation