28INR0213 · BESS · Upton County
Badger BESS
Badger BESS is a 139 MW battery storage project in Upton County, Texas, connecting at Tap 345kV 59903 Bearkat - 76000 L_NORTMC5_1Y. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/25/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0213
- Capacity
- 139 MW
- Fuel
- BESS (BA)
- County
- Upton County
- Interconnecting entity
- Greasewood BESS, LLC
- Projected COD
- 05/25/2029
- Entered queue
- 11/27/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Capacity 154 → 139 MW
- 11/27/2024Entered the queue with 154 MW, projected COD 05/25/2029
- 11/27/2024Screening → FIS Requested
Other projects at this substation
| Badger Solar | Solar | 280 MW | FIS Requested |