ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0182 · Solar · Navarro County

Ponferrada Solar

Ponferrada Solar is a 149 MW solar project in Navarro County, Texas, connecting at Tap 138 KV 3456 CORSWEST1_8 - 3457 CORS_MOBT_8. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/06/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0182
Capacity
149 MW
Fuel
Solar (PV)
Interconnecting entity
Karol Solar VI
Projected COD
04/06/2029
Entered queue
10/01/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/15/2025
    Screening → FIS Requested
  • 10/01/2024
    Entered the queue with 149 MW, projected COD 04/06/2029

Other projects at this substation

No other projects at this substation.