ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0177 · Solar · Ector County

Sisters Solar II

Sisters Solar II is a 206 MW solar project in Ector County, Texas, connecting at tap 345kV 11010 Wolf Switching Station - 10012 Meteor. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 12/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0177
Capacity
206 MW
Fuel
Solar (PV)
Interconnecting entity
Oberon Solar III, LLC
Projected COD
12/15/2028
Entered queue
10/18/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/27/2026
    FIS Requested → FIS Approved
  • 10/18/2024
    Entered the queue with 206 MW, projected COD 12/15/2028
  • 10/18/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.