ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0150 · BESS · Fayette County

South Tripoint BESS

South Tripoint BESS is a 204 MW battery storage project in Fayette County, Texas, connecting at 7286 L_FAYETT8_1Y 138kV. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 05/30/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0150
Capacity
204 MW
Fuel
BESS (BA)
Interconnecting entity
South Triangle Energy, LLC
Projected COD
05/30/2030
Entered queue
12/19/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/19/2024
    Entered the queue with 204 MW, projected COD 05/30/2030

Other projects at this substation

No other projects at this substation.