ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0147 · Solar · Falls County

Fallstone Solar SLF

Fallstone Solar SLF is a 60 MW solar project in Falls County, Texas, connecting at Tap 69kV 3588 Groesbeck - 3637 Otto Junction. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/21/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0147
Capacity
60 MW
Fuel
Solar (PV)
Interconnecting entity
Fallstone Solar, LLC
Projected COD
09/21/2028
Entered queue
12/04/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/04/2024
    Entered the queue with 60 MW, projected COD 09/21/2028
  • 12/04/2024
    Screening → FIS Requested

Other projects at this substation

Fallstone Storage SLFBESS0 MWFIS Requested