28INR0147 · Solar · Falls County
Fallstone Solar SLF
Fallstone Solar SLF is a 60 MW solar project in Falls County, Texas, connecting at Tap 69kV 3588 Groesbeck - 3637 Otto Junction. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/21/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0147
- Capacity
- 60 MW
- Fuel
- Solar (PV)
- County
- Falls County
- Interconnecting entity
- Fallstone Solar, LLC
- Projected COD
- 09/21/2028
- Entered queue
- 12/04/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/04/2024Entered the queue with 60 MW, projected COD 09/21/2028
- 12/04/2024Screening → FIS Requested
Other projects at this substation
| Fallstone Storage SLF | BESS | 0 MW | FIS Requested |