ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0127 · Solar · Starr County

Half Moon Solar

Half Moon Solar is a 512 MW solar project in Starr County, Texas, connecting at #80231 Pronto 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0127
Capacity
512 MW
Fuel
Solar (PV)
Interconnecting entity
NextEra Energy Interconnection Holdings, LLC
Projected COD
07/01/2029
Entered queue
12/23/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/08/2025
    FIS Requested → IA Signed
  • 12/23/2024
    Entered the queue with 512 MW, projected COD 07/01/2029
  • 12/23/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.