28INR0104 · BESS · La Salle County

Vazlon BESS SLF

Withdrawn

Vazlon BESS SLF is a 0 MW battery storage project in La Salle County, Texas, connecting at 8619 Encinal - 8627 Lemay Box Bay 138kV line. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0104
Capacity
0 MW
Fuel
BESS (BA)
Interconnecting entity
Vazlon Energy LLC
Projected COD
06/30/2028
Entered queue
09/06/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/29/2026
    Listed as inactive
  • 09/06/2024
    Entered the queue with 0 MW, projected COD 06/30/2028