LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0090 · Gas · Wharton County

EmberGreen

EmberGreen is a 1,036 MW natural gas project in Wharton County, Texas, connecting at Tap 138kV 48050 Caney - 44150 Hungerford. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0090
Capacity
1,036 MW
Fuel
Gas (GT)
Interconnecting entity
EmberGreen Energy Center
Projected COD
01/01/2028
Entered queue
06/13/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/04/2026
    FIS Approved → IA Signed
  • 04/21/2026
    FIS Requested → FIS Approved
  • 12/18/2024
    Screening → FIS Requested
  • 06/13/2024
    Entered the queue with 1,036 MW, projected COD 01/01/2028

Other projects at this substation

No other projects at this substation.