28INR0086 · Gas · Upton County
West Royal Natural Gas (TEF-Due Diligence)
West Royal Natural Gas (TEF-Due Diligence) is a 888 MW natural gas project in Upton County, Texas, connecting at Tap 345kV 76000 L_NORTMC5_1Y - 18668 ROCKDRAW_5. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0086
- Capacity
- 888 MW
- Fuel
- Gas (GT)
- County
- Upton County
- Interconnecting entity
- Invenergy Energy Transition Development LLC
- Projected COD
- 06/01/2030
- Entered queue
- 06/13/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/17/2024Screening → FIS Requested
- 06/13/2024Entered the queue with 888 MW, projected COD 06/01/2030