28INR0068 · Solar · Wharton County
Alpujarra Solar
Alpujarra Solar is a 112 MW solar project in Wharton County, Texas, connecting at 5521 GALOW 138 KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0068
- Capacity
- 112 MW
- Fuel
- Solar (PV)
- Substation
- 5521 GALOW 138 KV
- County
- Wharton County
- Interconnecting entity
- Greening USA Corp.
- Projected COD
- 05/01/2028
- Entered queue
- 08/12/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/12/2024Entered the queue with 112 MW, projected COD 05/01/2028
- 08/12/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.