28INR0024 · BESS · Bexar County
Padua Grid BESS Unit 3
Padua Grid BESS Unit 3 is a 201 MW battery storage project in Bexar County, Texas, connecting at Tap #5395 O.W Sommer 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 05/15/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0024
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- Tap #5395 O.W Sommer 138kV
- County
- Bexar County
- Interconnecting entity
- Padua Grid 3, LLC
- Projected COD
- 05/15/2026
- Entered queue
- 03/01/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/22/2026Energization Approved → Sync Approved
- 06/12/2026IA Signed → Energization Approved
- 06/20/2025FIS Requested → FIS Approved
- 03/07/2025FIS Approved → IA Signed
- 03/01/2024Entered the queue with 201 MW, projected COD 05/15/2026
- 03/01/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.