28INR0020 · BESS · Bexar County
Caracara Energy Storage Center
Caracara Energy Storage Center is a 203 MW battery storage project in Bexar County, Texas, connecting at Tap 138kV 5055 Cagnon - 5346 Potranco. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0020
- Capacity
- 203 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV 5055 Cagnon - 5346 Potranco
- County
- Bexar County
- Interconnecting entity
- FRESH AIR ENERGY II, LLC
- Projected COD
- 08/01/2028
- Entered queue
- 05/09/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/05/2024Screening → FIS Requested
- 05/09/2024Entered the queue with 203 MW, projected COD 08/01/2028
Other projects at this substation
No other projects at this substation.