LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0020 · BESS · Bexar County

Caracara Energy Storage Center

Caracara Energy Storage Center is a 203 MW battery storage project in Bexar County, Texas, connecting at Tap 138kV 5055 Cagnon - 5346 Potranco. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0020
Capacity
203 MW
Fuel
BESS (BA)
Interconnecting entity
FRESH AIR ENERGY II, LLC
Projected COD
08/01/2028
Entered queue
05/09/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/05/2024
    Screening → FIS Requested
  • 05/09/2024
    Entered the queue with 203 MW, projected COD 08/01/2028

Other projects at this substation

No other projects at this substation.