28INR0005 · Solar · Zapata County
Tetris Solar
Tetris Solar is a 359 MW solar project in Zapata County, Texas, connecting at TAP 345kV 80307 Del Sol 7C - 80225 Cenizo 7C. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0005
- Capacity
- 359 MW
- Fuel
- Solar (PV)
- County
- Zapata County
- Interconnecting entity
- NextEra Energy Interconnection Holdings LLC
- Projected COD
- 07/01/2029
- Entered queue
- 07/21/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/21/2023Entered the queue with 359 MW, projected COD 07/01/2029
- 07/21/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.