ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0631 · Gas · Hunt County

Power Lane II - Gas

Power Lane II - Gas is a 104 MW natural gas project in Hunt County, Texas, connecting at GREENV_IN_8 (977) via (future) GEUS_STM Substation. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/15/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0631
Capacity
104 MW
Fuel
Gas (IC)
Interconnecting entity
GEUS
Projected COD
08/15/2027
Entered queue
08/17/2026
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/17/2026
    Entered the queue with 104 MW, projected COD 08/15/2027
  • 08/17/2026
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.