27INR0620 · BESS · Pecos County
st gall IIIA Storage
st gall IIIA Storage is a 201 MW battery storage project in Pecos County, Texas, connecting at 38355 LEON_CRK 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0620
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 38355 LEON_CRK 138kV
- County
- Pecos County
- Interconnecting entity
- Tempus Power Management LLC
- Projected COD
- 06/01/2028
- Entered queue
- 03/17/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/17/2026Entered the queue with 201 MW, projected COD 06/01/2028
- 03/17/2026Screening → FIS Requested
Other projects at this substation
| st gall IIIB Storage | BESS | 201 MW | FIS Requested |