27INR0571 · BESS · Parker County

Nabla Energy Storage I

Nabla Energy Storage I is a 750 MW battery storage project in Parker County, Texas, connecting at Double Tap 345kV Parker (1436) - Benbrook (1873 & 1869) DCKT. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/17/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0571
Capacity
750 MW
Fuel
BESS (BA)
Interconnecting entity
Nabla Park LLC
Projected COD
09/17/2029
Entered queue
10/30/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/30/2025
    Entered the queue with 750 MW, projected COD 09/17/2029
  • 10/30/2025
    Screening → FIS Requested

Other projects at this substation

Nabla Energy Storage IIBESS750 MWFIS Requested