27INR0570 · Solar · Ector County
Sisters Solar - Phase 2
Sisters Solar - Phase 2 is a 202 MW solar project in Ector County, Texas, connecting at 10009 McGee 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/23/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0570
- Capacity
- 202 MW
- Fuel
- Solar (PV)
- Substation
- 10009 McGee 345 kV
- County
- Ector County
- Interconnecting entity
- Oberon Solar IV, LLC
- Projected COD
- 09/23/2028
- Entered queue
- 07/22/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/22/2026Entered the queue with 202 MW, projected COD 09/23/2028
- 07/22/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.