ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0510 · Wind · Pecos County

Pecos Wind

Pecos Wind is a 194 MW wind project in Pecos County, Texas, connecting at Tap 345 kV 60404 Solstice (SOLSTICE7A) – 76002 Bakersfield (L_BAKERS5_1Y). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0510
Capacity
194 MW
Fuel
Wind (WT)
Interconnecting entity
Midnight Energy Center, LLC
Projected COD
05/30/2028
Entered queue
07/07/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/18/2026
    Screening → IA Signed
  • 07/07/2025
    Entered the queue with 194 MW, projected COD 05/30/2028

Other projects at this substation

No other projects at this substation.