27INR0500 · Solar · Borden County
Antila Solar
Antila Solar is a 500 MW solar project in Borden County, Texas, connecting at #59916 Buck Canyon 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/30/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0500
- Capacity
- 500 MW
- Fuel
- Solar (PV)
- Substation
- #59916 Buck Canyon 345kV
- County
- Borden County
- Interconnecting entity
- Antila Solar LLC
- Projected COD
- 11/30/2027
- Entered queue
- 04/02/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/13/2025FIS Requested → IA Signed
- 04/02/2025Entered the queue with 500 MW, projected COD 11/30/2027
- 04/02/2025Screening → FIS Requested
Other projects at this substation
| Juno 3 Solar | Solar | 500 MW | IA Signed |