LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0488 · Solar · Rusk County

Dry Creek Solar II

Dry Creek Solar II is a 201 MW solar project in Rusk County, Texas, connecting at Dorsett 345 kV Switching Station(tap 345 kV 3100 Martin Lake - 3105 Elkton). ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 02/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0488
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Oak Hill Solar II LLC
Projected COD
02/01/2028
Entered queue
06/02/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Capacity 202 → 201 MW
  • 09/15/2026
    FIS Requested → FIS Approved
  • 06/02/2025
    Entered the queue with 202 MW, projected COD 02/01/2028
  • 06/02/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.