27INR0422 · BESS · Ector County
M-Bar BESS I
M-Bar BESS I is a 82 MW battery storage project in Ector County, Texas, connecting at 1141 Holt Switch Substation 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/18/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0422
- Capacity
- 82 MW
- Fuel
- BESS (BA)
- Substation
- 1141 Holt Switch Substation 138 kV
- County
- Ector County
- Interconnecting entity
- M-Bar Energy I, LLC
- Projected COD
- 09/18/2028
- Entered queue
- 12/13/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/13/2024Entered the queue with 82 MW, projected COD 09/18/2028
- 12/13/2024Screening → FIS Requested