ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0392 · BESS · Wharton County

Cernan BESS

COD delayed 1×

Cernan BESS is a 10 MW battery storage project in Wharton County, Texas, connecting at Hillje 345kV (#44200). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/02/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0392
Capacity
10 MW
Fuel
BESS (BA)
Interconnecting entity
Cernan BESS LLC
Projected COD
10/02/2028
Entered queue
01/30/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/01/2027 → 10/02/2028 (+12 months)
  • 12/30/2025
    FIS Approved → IA Signed
  • 10/31/2025
    FIS Requested → FIS Approved
  • 01/30/2025
    Entered the queue with 10 MW, projected COD 10/01/2027
  • 01/30/2025
    Screening → FIS Requested